Flooring & Tiling · Glossary Term

Screeding: Meaning, Tools Used and Surface Levelling Steps

What screeding means, the tools masons use, and the steps that turn a rough slab into a flat base for tiles.

On this page
  1. What Is Screeding in Construction?
  2. Which Screed Type Suits Your Floor?
  3. What Tools Are Used for Screeding?
  4. How Do You Level a Floor Surface, Step by Step?
  5. How Flat Should the Finished Screed Be?
  6. DIY or Professional: Who Should Do the Work?
  7. Where Is Screed Used in Homes and Offices?
Summary — what you need to know
  • Screeding strikes a fresh layer off to a set level.
  • Levels come from a datum line, dots and screed strips, not from eyeballing.
  • A screed board levels; floats and trowels finish.
  • IS 2571:1970 asks for 15 days of moist curing and 28 days before regular traffic.

Screeding is the process of spreading cement-sand mortar, concrete or liquid screed over a floor slab and striking it off to a flat, set level. The layer, called screed, gives tiles a true base.

25 mm
Minimum bonded sand-cement screed (Concrete Centre)
15 days
Minimum moist curing for in-situ floors (IS 2571:1970)
3 mm
Largest gap under a 2 m straightedge, class SR1 (BS 8204)

What Is Screeding in Construction?

Screeding in construction means levelling a fresh layer with a straight board run over guides set at the correct height. IS 2571:1970, the Indian code of practice for laying in-situ cement concrete flooring, describes this screed-board method.

On site, "screed" has three meanings: the board (the tool), the guide strip (screed strip or rail) and the levelled layer itself. In Hindi, screeding is simply described as making a surface level (सतह को समतल करना).

Screeding vs plastering vs punning

Screeding levels floors. Plastering covers walls and ceilings with cement-sand mortar. Punning is a thin finishing coat, often POP (Plaster of Paris), over plaster before paint.

Searches for "wall screeding" usually mean a POP or putty skim coat on walls, a usage common in Nigeria.

Which Screed Type Suits Your Floor?

Choose by how the screed meets the slab: bonded on a sound slab, unbonded or floating over a membrane or insulation.

Screed types and thickness

Concrete Centre guidance (BS 8204)
TypeHow it sitsThicknessTypical use
Bonded CommonStuck to the slab with slurry25 mm min; 40 mm ±15 mm specifiedLevelling over sound RCC slabs
UnbondedOn a damp-proof membrane50 mm min; 70 mm designOver a membrane or weak floor
FloatingOn insulation or an acoustic layer35 mm min (pumpable calcium sulphate)Sound-insulated or heated floors
Liquid FastPumped; flows near level25 mm min bondedLarge areas, up to 2,000 m² a day

What Tools Are Used for Screeding?

Screeding tools fall into three groups: tools that set the level, tools that strike it off and tools that finish the surface.

Floor screeding tools by stage

Hand tools first, machines last
ToolWhat it doesStage
Water level or laser levelCarries one datum height to every wallSetting levels
Screed strips or railsMortar, timber or pipe guides at finished heightSetting levels
Tamping boardCompacts the mix between stripsLevelling
Screed board Key toolStrikes off excess over the stripsLevelling
Wooden floatEvens the surface and closes small holesFinishing
Steel trowelGives a smooth, dense topFinishing
Power or vibrating screedMotorised board for large slabsLevelling
Laser screed machine CommercialLaser-guided head sets the height automaticallyLevelling

Homes need only hand tools. Laser screeds and screeding robots suit large commercial floors; maker Somero claims under 4 hours for a pour that took a crew 4 to 5 days.

How Do You Level a Floor Surface, Step by Step?

Level a floor by fixing one datum, setting dots and strips to it, then striking off each bay with a screed board.

Screed set-out: datum line 1,000 mm above floor level, mortar dots, screed strips and a screed board, with a plan of bays
  1. Clean the slab. Soak a hardened base for at least 12 hours and mop off surplus water (IS 2571).
  2. Mark a datum line on every wall, for example 1,000 mm above finished floor level, with a water level or laser. A datum works like a benchmark in levelling in surveying.
  3. Measure down from the datum and fix mortar pads (dots) at screed height, close enough for the board to span two.
  4. Join the dots into screed strips. On a hardened base, IS 2571 limits panels to 2 m a side.
  5. On bonded work, brush neat cement slurry on just ahead of the mix.
  6. Fill a bay, tamp it, and pull the screed board across the strips in a sawing motion. Fill hollows, strike again, then wood-float.
  7. For a trowelled finish, IS 2571 calls for three passes over 1 to 6 hours.
  8. Keep it moist for at least 15 days under wet gunny bags, damp sand or ponded water.
Worked exampleReading screed depth from a datum (illustrative numbers)
Datum line above finished floor level1,000 mm
Point A: datum to slab 1,045 mm, so 1,045 − 1,00045 mm
Point B: datum to slab 1,062 mm, so 1,062 − 1,00062 mm
Point C: datum to slab 1,038 mm, so 1,038 − 1,00038 mm
Bonded range, 40 mm ±15 mm25–55 mm
A and C fit; B is 7 mm too deepFill or redesign at B
Do not overwork wet screed

IS 2571 asks for light early trowelling; heavy passes draw weak laitance to the top. In Bengaluru's hot, dry months, cover bays early and keep panels smaller.

How Flat Should the Finished Screed Be?

Check flatness with a 2 m straightedge laid in several directions. BS 8204's strictest class, SR1, allows a 3 mm gap; SR2 and SR3 allow more.

  • Hollow sound when tapped with a rod (poor bond)
  • Cracks wider than a hairline
  • Dusty surface that rubs off under a shoe

Before wood, vinyl or epoxy flooring, let sand-cement screed dry about 1 day per mm up to 50 mm (BS 8203): roughly 40 days for 40 mm.

DIY or Professional: Who Should Do the Work?

Hire a mason for whole rooms and floors with falls; a homeowner can patch-level small areas.

DIY

Small jobs

Patch repairs, small rooms.

  • Saves labour cost
  • Fine for patch levelling
  • Hard to keep large bays flat

Professional mason

Recommended

Whole floors and wet areas.

  • Sets datum and falls correctly
  • Finishes faster with a crew
  • Adds labour cost; get a written quote

Where Is Screed Used in Homes and Offices?

Homes use screed under tiles and on bathroom falls and terraces; offices and warehouses use it for large flat or heated floors.

  • Levelling bed under floor tiles and stone
  • Bathroom and balcony floors laid to falls towards the drain
  • Terrace and roof screeds laid to slope for rainwater
Before you start

Confirm finished floor levels at doors with your architect first. Changing them later means cutting door frames.

60-minute delivery

Planning to screed a floor?

Cement, tools and tiles delivered across Bengaluru.

CementHand ToolsMeasuring ToolsFloor Tiles
Shop nowGet a price listBengaluru · open 8 am–8 pm, all days

Frequently Asked Questions

What is the purpose of screeding?

Screeding gives the final floor a flat base at the right height. It also evens out slab dips and sets drainage slopes.

What does screeding mean?

Screeding means striking a fresh layer off level with a straight board run over guides. The word also names the board, the strips and the layer.

What is the process of screeding?

Clean and soak the base, mark a datum, set dots and strips, then fill and strike off each bay. Float, trowel if needed and moist-cure for 15 days (IS 2571:1970).

What are the different types of screeding?

Bonded, unbonded, floating and liquid (self-smoothing) screeds. Heated screed carries underfloor heating pipes.

What are the best practices for conducting home screeding?

Work from one datum, keep bays small and never add water to a stiffening mix. Cure under wet gunny bags and check with a 2 m straightedge.

What is the difference between bonded and unbonded screeds?

Bonded screed sticks to the slab and can be 25 mm thin. Unbonded screed sits on a membrane and needs at least 50 mm, 70 mm by design (Concrete Centre).

What materials are used in traditional cement sand screeds?

Cement, clean sharp sand and water, typically 1:3 to 1:4.5 cement to sand (Concrete Centre). Fibres or fine mesh help control cracking.

What factors should be considered when specifying screed depth and type?

Consider slab condition, any membrane, insulation or pipes underneath, the floor finish and drying time. Sand-cement screed dries about 1 day per mm up to 50 mm.

Reviewed by

HomeRun Team

The HomeRun editorial team researches and writes our building guides.