Planning, Land & Approvals · How-to Guide

Land Conversion Certificate: Process, Documents and Fees

How to convert agricultural land for a house or layout in Karnataka, what the 2025 Section 95 changes mean for Bengaluru plots, which documents to file, and what the fees depend on.

On this page
  1. What Is a Land Conversion Certificate and Why Is It Important?
  2. Does Your Property Need a Land Conversion Certificate?
  3. What Are the New Rules for Land Conversion in Karnataka?
  4. How Do You Get a Land Conversion Certificate Online in Karnataka?
  5. What Documents Are Required for Land Conversion in Karnataka?
  6. How Much Does a Land Conversion Certificate Cost in Karnataka?
  7. What Mistakes Should You Avoid During Land Conversion?
  8. How Does Land Conversion Affect Property Tax?
  9. What Should You Do After the Conversion Order Is Issued?
0%
Summary — what you need to know
  • A land conversion certificate is the official order that lets agricultural land be used for a non-agricultural purpose such as a house, layout or shop.
  • In Karnataka, it is issued under Section 95 of the Karnataka Land Revenue Act, 1964, and is often called a DC conversion.
  • Since the 2025 rule changes, land inside an approved master plan is converted through the planning authority, without a separate DC order.
  • Outside master plans, the DC has 30 days to decide on an affidavit-based application before deemed conversion applies.
  • Rules, fees and timelines change often. Confirm with the Tahsildar or DC office before you pay or file.

A land conversion certificate is the government order that changes the permitted use of a plot from agricultural to non-agricultural, so you can legally build a house, a layout or a commercial building on it. Without it, banks rarely lend, plans are not sanctioned and the property is hard to sell.

This guide covers the Karnataka process in detail. For the records you will file with it, see our guides to land survey records and what a title deed is.

30 days
Time the DC has to decide an application outside master plan limits
15 days
Time Tahsildars and other departments get to give their opinion
₹200
Minimum stamp paper value for the Form 21B or 21C affidavit

What Is a Land Conversion Certificate and Why Is It Important?

A land conversion certificate, also called a conversion order or NA (non-agricultural) order, is the revenue authority's written permission to use agricultural land for another purpose. In Karnataka, it is commonly called a DC conversion because the Deputy Commissioner of the district traditionally grants it.

The certificate matters at three points in a property's life:

  • Building approval: local bodies and planning authorities need proof that the land use permits construction.
  • Home loans: lenders check conversion before funding a plot or house on former farmland.
  • Sale and khata: buyers, sub-registrars and local bodies look for the order before treating a plot as a residential site.
Insight: conversion is not ownership

A conversion order changes how land may be used. It does not prove who owns it. Check title separately through the sale deed, encumbrance certificate and RTC before you buy a converted plot.

Does Your Property Need a Land Conversion Certificate?

Your property needs a land conversion certificate if its revenue record still shows it as agricultural land and you plan to build, sell plots or run a business on it. Land already inside an approved layout, with a valid khata from a local body, has usually been converted earlier.

How to check if land is DC converted

  • Download the current RTC (Record of Rights, Tenancy and Crops, also called pahani) from Bhoomi and check whether it records the land as converted.
  • Ask the seller for the conversion order number and date, and verify the order on the Karnataka land conversion portal.
  • Check the master plan land use for the survey number with the local planning authority.
  • Look for a khata or e-khata from the city corporation, municipality or gram panchayat.
  • Read the encumbrance certificate for any earlier conversion or cancellation entries.

What Are the New Rules for Land Conversion in Karnataka?

The new rules split land conversion in Karnataka into two routes: planning-authority conversion inside approved master plans and affidavit-based DC conversion everywhere else. They come from amendments to Section 95(2) of the Karnataka Land Revenue Act and new Rules 106B to 106F of the Karnataka Land Revenue Rules.

Flowchart: check the RTC for agricultural status, then follow the planning-authority route inside a master plan or the six-step DC conversion route in Karnataka

Inside an approved master plan

Bengaluru, cities

  • No separate DC permission if your use matches the zoning
  • Fee under Section 95(7) paid to the planning authority
  • Filed with the layout or building plan application
  • Form 21B affidavit is mandatory

Outside master plan limits

Rural land

  • Online application to the Deputy Commissioner
  • Departments give opinions within 15 days
  • Deemed conversion if the DC misses the deadline
  • Form 21C affidavit is mandatory

An Urban Development Department circular dated 18 February 2026 told planning authorities, including the Bangalore Development Authority and the Greater Bengaluru Authority, not to accept standalone conversion applications for master plan land. Conversion is processed along with the layout or plan approval.

Reports also say small industries on up to 2 acres and renewable energy projects get automatic conversion without DC approval.

Sources differ on dates and deadlines

One legal summary cites Gazette notification RD-LGP/6/2025 dated 17 September 2025. Others say the rules took effect on 23 December 2025. Some sources describe the DC deadline as 15 days with deemed approval after 30 days; others say 30 days, or 30 working days. Confirm the current position with the Tahsildar or DC office.

How Do You Get a Land Conversion Certificate Online in Karnataka?

You get a land conversion certificate online in Karnataka by filing an affidavit-based application with your land records, paying the fee and downloading the digitally signed order. The steps below follow the route outside master plan limits.

  1. Confirm the land use: check the RTC, the survey sketch and the master plan or zonal status of the survey number.
  2. Prepare the affidavit: Form 21C (or Form 21B for master plan land) on non-judicial stamp paper of at least ₹200, notarised.
  3. File online: apply through the Bhoomi land conversion service with the affidavit, RTC, mutation extract and sketch.
  4. Department review: the Tahsildar and other departments, such as Forest, give their opinion; silence within 15 days counts as no objection.
  5. DC decision: the Deputy Commissioner approves or rejects; if no decision comes in time, the file moves to your login for fee payment.
  6. Pay the conversion fee: pay online against the demand shown for your survey number.
  7. Download the order: the final conversion order is issued digitally and can be downloaded from the land conversion portal.
Day 0

Application filed

Affidavit and records uploaded online.

Day 5

Case worker check

The DC office case worker reviews the file.

Day 15

Opinions due

Tahsildar and other departments respond, or are treated as having no objection.

Day 30

Decision or deemed conversion

The DC decides; otherwise deemed conversion applies after fee payment.

These are the deadlines reported for the 2025 rules. Files with tenancy, title or land-grant issues can take longer.

What Documents Are Required for Land Conversion in Karnataka?

The documents required for a land conversion certificate in Karnataka are the affidavit, the current RTC, the mutation register extract, a survey sketch and proof of ownership. Extra papers apply to granted, tenanted or lake-side land.

Land conversion documents in Karnataka

Verify the current list with the Revenue Department
DocumentPurposeWhere to get it
Affidavit (Form 21B or 21C) MandatoryDeclares ownership, purpose and legal complianceNotary, ₹200+ stamp paper
RTC (pahani)Shows owner, extent and current land useBhoomi
Mutation register extractShows how ownership changed handsBhoomi or Tahsildar office
Survey sketch (11E or pre-conversion sketch)Marks the exact area to be convertedSurvey Settlement and Land Records Department
Sale, partition or grant deedProves titleSub-registrar office or Kaveri
Master plan or zonal extractConfirms permitted land useLocal planning authority
NOCs If applicableForest, lake buffer, highway or land tribunal clearanceConcerned department
Aadhaar and PAN of every owner are usually needed for the affidavit and online login.

How Much Does a Land Conversion Certificate Cost in Karnataka?

A land conversion certificate in Karnataka costs the conversion fee under Section 95(7), plus the affidavit and any professional charges. The Revenue Department sets the fee by location, district and end use, so residential use in rural areas pays least and commercial use near cities pays most.

Conversion fee figures quoted online

Indicative only, not an official schedule
LocationResidential (₹)Commercial (₹)
Near a city corporation327654
Taluk centre218327
Rural area89218
Repeated by several property websites without the notification number or the unit of area. Treat them as a rough guide and use the demand shown on the portal for your survey number.
Note: other states charge differently

Land conversion fees in Tamil Nadu, Andhra Pradesh, Telangana, Kerala and West Bengal follow each state's own law. Check the state revenue portal for current rates.

What Mistakes Should You Avoid During Land Conversion?

The mistakes that most often delay or void a land conversion are mismatched records, wrong land use and building before the order is issued. Watch for these red flags.

  • The name or extent on the RTC does not match the sale deed or sketch.
  • The intended use, such as commercial, conflicts with master plan zoning.
  • Construction starts before the conversion order is issued.
  • The seller shows a paper order that cannot be verified on the portal.
  • Granted, tenanted or lake-buffer land is filed without the required NOC.
  • Converted land is used for a different purpose than the one approved.

Misuse can lead to cancellation, forfeiture of fees and fines. Reports on the 2025 rules cite fines of up to ₹1 lakh plus ₹2,500 per day for continuing violations, recorded as an encumbrance on the RTC.

How Does Land Conversion Affect Property Tax?

Land conversion moves a plot from agricultural land revenue to property tax charged by the local body, which is usually higher. The city corporation, municipality or gram panchayat assesses tax once it issues a khata for the converted site.

Insight: higher tax, higher value

Converted land costs more to hold each year, but it can be mortgaged, built on and sold as a residential site. Conversion can also change how income tax treats a later sale, so ask a chartered accountant before you sell.

What Should You Do After the Conversion Order Is Issued?

After the conversion order is issued, update the revenue and local body records, then apply for building approvals. Keep certified copies of the order with your title papers.

  • Check that the RTC now shows the land as converted for the approved purpose.
  • Apply for a khata or e-khata with the city corporation, municipality or gram panchayat.
  • Get layout or building plan sanction from the planning authority.
  • Obtain a commencement certificate before work starts on site.
  • Build only as sanctioned, then apply for an occupancy certificate on completion.
  • Download and save the digitally signed order and fee receipt.
60-minute delivery

Plot approved and ready to build?

Order foundation materials delivered across Bengaluru.

CementTMT BarsBricks & BlocksSand & Aggregates
Shop nowGet a price listBengaluru · open 8 am–8 pm, all days
This guide is general information, not legal advice

Land conversion rules in Karnataka changed in 2025 and 2026 and may change again. Confirm the current procedure, fees and timelines with the Tahsildar or Deputy Commissioner's office, or a property lawyer, before you file or buy.

Frequently Asked Questions

What is a conversion certificate in land?

A conversion certificate is the official order that allows agricultural land to be used for a non-agricultural purpose, such as housing or commerce. In Karnataka, it is issued under Section 95 of the Karnataka Land Revenue Act, 1964.

How to get land conversion certificate online in Karnataka?

File an affidavit-based application online through the Bhoomi land conversion service with your RTC, mutation extract and sketch. After review and fee payment, download the digitally signed order from the land conversion portal. Inside master plan areas, apply through the planning authority with your plan approval instead.

What are the new rules for converting land in Karnataka?

Under the 2025 amendments, land inside an approved master plan needs no separate DC order if its use matches the zoning; the planning authority collects the fee. Outside master plans, the DC must decide within a fixed period, after which deemed conversion applies. Confirm the exact deadlines with the DC office, as sources differ.

How to check if land is DC converted or not?

Check the RTC on Bhoomi for a conversion entry and verify the conversion order number on the Karnataka land conversion portal. You can also ask the Tahsildar office or check for a khata from the local body.

Why is a conversion certificate important?

Without it, you cannot legally build on agricultural land, get plan sanction or a khata as a residential site, and most banks will not lend. It also protects buyers from penalties and demolition orders later.

What documents are required to apply for a conversion certificate in Karnataka?

You need a notarised Form 21B or 21C affidavit, the current RTC, the mutation register extract, a survey sketch, proof of title and a master plan extract where relevant. Granted, tenanted or lake-side land needs extra NOCs.

How long does it take to process a conversion certificate?

Outside master plans, the 2025 rules give the DC about 30 days to decide, with deemed conversion if the deadline passes. Files with title or tenancy problems can take several months. Inside master plans, conversion runs alongside the plan approval.

What are the consequences of not obtaining a conversion certificate?

Building without conversion can lead to penalty notices, fines and demolition orders. The property may not get plan sanction, a khata or an occupancy certificate, which makes it hard to finance or sell.

Reviewed by

HomeRun Team

The HomeRun editorial team researches and writes our building guides.